Category Archives: Nottingham Express Transit

In Pictures: Testing continues on NET Phase Two

For the first time in a while daytime testing has not been extended in the past week (mainly because it is already running on both lines in their entirety!) and trams are starting to become a more regular occurrence to … Continue reading

Posted in Nottingham Express Transit | 2 Comments

NET Phase Two testing extended to complete length of both lines

It has been another week of key milestones for the Nottingham Express Transit Phase Two project with the extension of daytime testing not once but twice in as many days. Beeston was reached for the first time in daylight hours … Continue reading

Posted in Nottingham Express Transit | Comments Off on NET Phase Two testing extended to complete length of both lines

NET services altered for Milk Race again

On Sunday 25th May Nottingham Express Transit services from Phoenix Park and Hucknall will be terminated at Royal Centre with replacement bus services from there to Station Street as a result of the Milk Race taking place in the city. … Continue reading

Posted in Nottingham Express Transit | Comments Off on NET services altered for Milk Race again

Daytime testing reaches Clifton terminus

Trams are now running on the whole Clifton line during daylight hours following the latest extension of testing on the Phase Two extension of Nottingham Express Transit. Previously testing and driver training on this line was only running as far … Continue reading

Posted in Nottingham Express Transit | 1 Comment

Daytime testing extends on Nottingham Express Transit Phase Two

The sight of trams on the Chilwell line of Nottingham Express Transit during daylight hours is now a common occurrence following the extension of daytime testing through the Queens Medical Centre and alongside University Boulevard. Daylight testing also continues as … Continue reading

Posted in Nottingham Express Transit | Comments Off on Daytime testing extends on Nottingham Express Transit Phase Two

Another new timetable for NET

Nottingham Express Transit are to introduce another new timetable from Monday 20th April this time improving the afternoon timetable. As you may remember during March a new timetable was introduced which saw a 3-5 minute frequency during the morning peak … Continue reading

Posted in Nottingham Express Transit | Comments Off on Another new timetable for NET

Trams reach Toton Park and Ride terminus

Trams have now run on the entire Nottingham Express Transit Phase Two extensions following the arrival of the first tram at the Toton Park and Ride site on the Chilwell line during the night of Wednesday 1st April. This comes … Continue reading

Posted in Nottingham Express Transit | Comments Off on Trams reach Toton Park and Ride terminus

Passengers remain satisfied with the UK’s tramways

Transport Focus – formerly Passenger Focus – carried out the second annual Tram Passenger Survey in Autumn 2015 and the results have recently been released showing that 90% of those questioned remain satisfied with the overall tram service with passengers … Continue reading

Posted in Blackpool Tramway, Edinburgh Trams, Manchester Metrolink, Nottingham Express Transit, South Yorkshire Supertram, West Midlands Metro | 4 Comments

NET testing reaches Clifton terminus

It seems a week cannot pass at the moment without another milestone being reached on the Nottingham Express Transit Phase Two extensions but this week’s milestone was quite a special one as a tram made it way all the way … Continue reading

Posted in Nottingham Express Transit | Comments Off on NET testing reaches Clifton terminus

Track works to cause disruption on NET over Easter

Nottingham Express Transit services will be suspended between The Forest and Wilkinson Street from Friday 3rd April until Wednesday 8th April to allow for a major upgrade of the tracks. The works need to be completed before the expansion of … Continue reading

Posted in Nottingham Express Transit | Comments Off on Track works to cause disruption on NET over Easter

NET Phase Two testing extends again

The testing and commissioning process on the Nottingham Express Transit Phase Two extensions has once again taken a step forward with both the first weekend daytime tests and the extension of overnight testing as far as University Boulevard on the … Continue reading

Posted in Nottingham Express Transit | 1 Comment

Enhanced peak time service coming on NET

Nottingham Express Transit are to introduce a new timetable from Monday 16th March which will see extra services running during the morning peak. The new timetable will feature trams running every seven-ten minutes from Hucknall and Phoenix Park which will … Continue reading

Posted in Nottingham Express Transit | 1 Comment

Your chance to nominate a name for a NET Citadis

Ever wanted to name a tram? Well now is your chance! Nottingham Express Transit are inviting members of the public to send in their nominations for the new Citadis trams and they will then make the decision as to which … Continue reading

Posted in Nottingham Express Transit | Comments Off on Your chance to nominate a name for a NET Citadis

NET Phase Two daytime testing extends

Another small step towards the opening of Nottingham Express Transit Phase Two has been reached with daytime testing extended through Compton Acres on the Clifton line. The first daytime test runs took place on Tuesday 24th February and the sight … Continue reading

Posted in Nottingham Express Transit | Comments Off on NET Phase Two daytime testing extends

NET delays after car and tram collide at High School

Nottingham Express Transit suffered delays for two hours on Friday 20th February after a car hit a tram close to the High School stop at approximately 1245. The car pulled out of a side street and hit the tram but … Continue reading

Posted in Nottingham Express Transit | Comments Off on NET delays after car and tram collide at High School

Daylight testing commences on NET Phase Two

The next step towards the start of public services on Nottingham Express Transit’s Phase Two extensions has been made with the commencement of daylight testing in The Meadows and on to Wilford Lane. The first test runs took place on … Continue reading

Posted in Nottingham Express Transit | 1 Comment

A new voice for NET

Regular travellers on Nottingham Express Transit will start to notice a new voice telling them the next stop over the next few weeks as the announcements have been re-recorded in preparation for the opening of the new lines later this … Continue reading

Posted in Nottingham Express Transit | Comments Off on A new voice for NET

Nottingham Express Transit’s Citadis trams and their two numbers

Since the first Alstom Citadis tram was delivered to Nottingham there has been a common question asked: what is the other number carried on the side of the trams? Each of the Citadis trams was delivered with a three digit … Continue reading

Posted in Nottingham Express Transit | 3 Comments

Woman hit by tram in Nottingham

A woman in her 70s was reported to have been hit by a tram between the stops at The Forest and Wilkinson Street on Nottingham Express Transit on Monday 19th January and had to be taken to hospital as a … Continue reading

Posted in Nottingham Express Transit | Comments Off on Woman hit by tram in Nottingham

Testing continues on NET Phase Two

As 2015 starts further testing has commenced on the Phase Two extension of Nottingham Express Transit with the first tram movements taking place into the centre of Clifton overnight on Wednesday 7th January. As with all previous first test runs … Continue reading

Posted in Nottingham Express Transit | Comments Off on Testing continues on NET Phase Two