Delay to Clifton NET Phase Two works

Work on Southchurch Drive and Farnborough Road in Clifton on the route of Nottingham Express Transit Phase Two has been postponed following discussions between the construction contractor Taylor Woodrow Alstom, the Highway Authority and local bus operators. The work was due to commence on Sunday 2nd February but delays in completing the first phase of works on Southchurch Drive has led to the decision to delay the next phase of works. It is likely to be a few weeks before the works start and it is planned to confirm this as soon as possible.