The ongoing rail replacement works on Stagecoach Supertram have now moved on to the University and subway area. The outbound track is currently being lifted ahead of new rail being laid whilst additional overnight work is also taking place in Kelvin area of Infirmary Road. This phase of works – which will be the last of 2014 – are due to be completed by mid September with no trams currently able to run beyond Sheffield City Centre with a replacement bus service in operation serving Malin Bridge and Middlewood. Photos provided by Stuart Cooke.

Three images taken on 27th August showing current progress on the rail replacement works around the subway near to University. (All Photos: Stuart Cooke)